HIGH SPRINGS ‒ The City of High Springs is moving along with the roadway projects planned for this month.

Already completed are the “Northwest 237th Street section that runs by the High Springs Brewery and the roadway on the north side of Bailey Estates,” said High Springs Public Information Officer Kevin Mangan.

On the verge of completion is Northwest 244th Street between Northwest 199th Lane and U.S. Highway 441 and the entrance to the Civic Center. City staff has worked closely with school administration and contractors to minimize impacts on student drop-off and pick-up at First Christian Academy as much as possible.

Still to be completed is the stretch of road on Northwest 238th Street that leads to the High Springs Sports Complex. Although no firm completion date is set, this road project is anticipated to be completed following the Northwest 244th Street and Civic Center projects, said Mangan. As with all road construction, drivers are advised to slow down and do not drive too fast for conditions, be alert and pay attention to the signs and be patient.

#     #     #

Email cwalker@

alachuatoday.com